CASE STUDY SNAPSHOTS

GOSOWONG

Client: Newcrest Mining Limited
Location: Indonesia
The Gosowong Gold Operation is one of the largest gold mines in Indonesia, located on
Halmahera Island.

After experiencing a breakdown in which a pinion tooth snapped, the mine placed an emergency call-out request to several different companies within Australia. HMR Engineering was the first to respond and was on-site in less than 48 hours.

HMR worked continuously to rebuild and install a new pinion.

 

ROSEMONT & MOOLART WELL GOLD MINES

Client: Regis Resources Limited
Location: Western Australia

Regis Resources Limited was quoted a minimum of eight days by a competitor to rebuild Apron Pan Feeders at its Rosemount and Moolart Well mines. HMR was able to complete the work in 3.5 days and is commended by the client for the quickest ever rebuild of this equipment.

 

SEPON GOLD & COPPER MINE

Client: Lane Xang Minerals Limited (Lxml)
Location: Laos

Sepon Mine is a gold & copper operation located in Savannakhet Province of Laos, operated by Lane Xang Minerals Limited.

During 2020 plant refurbishment, HMR built a linishing machine on site, and refurbished the discharge end of a trunnion and seating area for a trunnion liner. On-site machining was carried out by HMR.

Latest Case Studies